#RoadWork will start September 13, 2021.

#RoadWork will start September 13, 2021. Learn more at bit.ly/3BU8Gyh

The start dates are:
SCHEDULE "A" SW 116th AVE – 9/13/2021
SCHEDULE "B" BEXLEY LN – 10/4/2021
SCHEDULE "C" MATADOR LN – 9/20/2021
SCHEDULE "D" MAJESTIC – 9/23/2021

Go to the King City Road Closures Helper App

Weather and other natural events can affect paving activities.